December 19, 2009

Crozet leaders anticipate a critical review of Yancey Mills Business Park in January

Reader comments (0) DailyProgress By Brian Wheeler
Charlottesville Tomorrow
Saturday, December 19, 2009

Albemarle County officials gathered more input on potential changes to the twenty-year Crozet Master Plan at a forum held Thursday evening.  The Crozet community continues to weigh in on modifications to the county’s first ever master plan, originally approved in 2004, which is now getting its first five-year review.

Mike Marshall, chair of the Crozet Community Advisory Council, welcomed an audience of about 40 residents to the third of five planned community forums on different aspects of the master plan.  Marshall said he didn’t think there would be much controversy about the matters on the evening’s agenda, however he foreshadowed concerns about the Yancey Mills Business Park proposal. 

Podcast produced by Charlottesville Tomorrow * Player by Odeo

Listen using player above or download the podcast:Download 20091217-Crozet-Forum3

20091217-Crozet-Marshall
Mike Marshall, Chair, Crozet Community Advisory Council
Marshall, an outspoken critic of the expansion of the growth area and business park, encouraged residents to each return with “15 or 20 friends” for the next forum being held January 21st.“The next forum is going to be about light industrial uses,” said Marshall. “This is a highly significant issue for Crozet and we need a good turnout and we need people to pay attention.  The Yancey’s have put in a comprehensive plan amendment which would create a 184-acre light industrial park at the southeast corner of the I-64 interchange.”

The Albemarle County Planning Commission will receive a highly anticipated report on issues related to light industrial zoning at their meeting January 19th.  Marshall said he wanted the advisory council to weigh in on that report, with feedback from Crozet residents, before the recommendations are considered by the Board of Supervisors in February.

Incoming Supervisor Rodney Thomas (Rio) said in a November interview that he was interested in finding new locations for light industrial businesses and that he was open to discussing the business park proposal in Crozet’s rural area. 

A year ago, the supervisors overturned a 6-1 vote by the planning commission to table the business park and directed that the Yancey Mills project be considered as part of the master plan review.  At the time, Supervisor Ken Boyd (Rivanna) expressed concern about leaving a decision that he said could have benefits for the entire county “in the hands of a relatively small group of people” in Crozet.

At the first two forums on the master plan revisions, the community discussed downtown Crozet and land use patterns.  The topics at Thursday’s meeting included transportation facilities, parks and greenways, and community facilities like libraries and schools.

20091217-Crozet “I think that the planning process is a good one,” said participant Mac Lafferty in an interview.  “I like the way that the county has broken it down into several different meetings. I  was pretty pleased with the participation we had last night.”

Lafferty, an engineer that previously lived in Crozet, was appointed last week by Supervisor Dennis Rooker to the county planning commission’s Jack Jouett seat.  His term begins in January.  Supervisor Ann Mallek was another local official in attendance at the forum.

On transportation, residents said they wanted a reexamination of a frontage road proposed by staff to run parallel to Route 250 in front of Brownsville Elementary and Henley Middle School.  The County’s Community Relations Manager, Lee Catlin, said she also heard residents express a high priority for trails and pedestrian connections that would allow people living in Western Ridge, Highlands  to get into downtown Crozet.

Mike Marshall said a pedestrian connection was also needed between downtown Crozet and Old Trail Village.

“We now have two economic centers that really are within walking distance, that are trying to emerge and get stronger,” said Marshall.  “We need to make it plain to people that you can walk there.”

After the fifth community forum is held in February, a summary of recommendations from staff and the public will be provided to the planning commission in March.  The Board of Supervisors is scheduled to start its review of the Crozet Master Plan revisions in June.

TIMELINE FOR PODCAST

  • 00:01:11 – Introduction by Mike Marshall, Chair, Crozet Community Advisory Council
  • 00:07:24 – Presentation by Elaine Echols, Albemarle County’s principal planner for the development areas
  • 00:10:30 – Echols describes timeline for master plan review.  Planning Commission to get recommendations in March 2010.  Recommendations go to Board of Supervisors in June 2010.
  • 00:11:19 – Echols reviews guiding principles and 2004 recommendations for transportation issues
  • 00:18:05 – Echols reviews staff recommendations for transportation changes in the master plan
  • 00:24:10 -- Echols discusses staff recommendation to maintain proposed frontage road in front of Brownsville Elementary and Henley Middle School, parallel to Route 250.
  • 00:25:09 -- Rebecca Ragsdale, Albemarle County Neighborhood Planner, starts staff presentation on parks and greenways
  • 00:26:19 – Ragsdale reviews guiding principles and 2004 recommendations for parks and greenways
  • 00:27:58 – Ragsdale reviews the limited staff recommendations for changes in the master plan related to parks and greenways
  • 00:31:38 – Ragsdale reviews guiding principles and 2004 recommendations for community facilities
  • 00:36:36 – Ragsdale reviews staff recommendations for community facilities in the master plan
  • 00:38:40 – Marshall asks residents for feedback on transportation issues.  Goal of road interconnections in 2004 master plan is discussed.
  • 00:40:35 – Marshall asks for discussion of proposed frontage road in front of Brownsville Elementary and Henley Middle School.  Resident questions value of this road.  Ragsdale describes benefit for traffic that would not need to get on Route 250.  Marshall says he doesn’t think it will contribute much benefit.  Parent describes benefit of road for student pick up and drop offs.
  • 00:48:18 – Marshall reflects that there are a number of concerns being raised about traffic congestion at the school.  Discussion of truck traffic and proposed Eastern Avenue.
  • 01:10:47 – County Transportation Engineer, Jack Kelsey, provides update on Jarmans Gap Road improvements.  He reports that VDOT’s staff cuts in right-of-way acquisition department is causing some delays.  Kelsey says there is a $900,000 gap funding shortfall on the project.
  • 01:16:00 – Marshall starts discussion of parks and greenways.
  • 01:19:30 – Marshall calls for a pedestrian connection between Downtown Crozet and Old Trail.
  • 01:22:00 -- Marshall starts discussion of community facilities.  Need for placeholder for a third elementary school is discussed.
  • 01:23:41 -- Recap of comments as captured by Lee Catlin, Albemarle’s Community Relations Manager

TrackBack

TrackBack URL for this entry:
http://www.typepad.com/services/trackback/6a00d834519bec69e20120a7646b6a970b

Listed below are links to weblogs that reference Crozet leaders anticipate a critical review of Yancey Mills Business Park in January:

Comments

Comment policy: First and last names are both required and anonymous comments are not allowed. Comments are moderated, and will not appear on this website until the editor has approved them.