« County Supervisors briefed on water and sewer issues; Whole Foods & Trader Joe’s may face added delays due to inadequate sewer capacity | Main | High Growth Coalition meets in Culpeper to discuss new state regulations impacting land use and transportation »

July 02, 2009

Board of Supervisors support Crozet stormwater management system; Cost higher than original estimate

By Julia Glendening
Charlottesville Tomorrow
Thursday, July 2, 2009

20090701-harper
Greg Harper, Water Resources Manager for Albemarle County

Greg Harper, the Water Resources Manager for Albemarle County, presented an update on the Crozet stormwater management system to the Board of Supervisors on July 1, 2009. The Board originally approved the system on November 7, 2007, however, the design was further developed and the 2009 cost estimate is larger than the 2007 estimate. The Board indicated their support for the stormwater project and agreed to reexamine the cost estimate at a future meeting.

Podcast produced by Charlottesville Tomorrow * Player by Odeo

Listen using player above or download the podcast: Download 20090701-crozet-stormwater

Harper described the goals of the project, which included stormwater management planning for future growth, especially a denser downtown area which he said could increase runoff. He also said the project would help to protect water resources by addressing areas currently without stormwater management. Harper stated the engineering plans are 80% complete and emphasized that staff hopes to provide stormwater management at the lowest cost possible.

A cost estimate was first provided in 2007 by Kimley-Horn Associates, the consultant for the project, and totaled $350,000. However, the estimate was changed in 2009 to $694,176. This was an increase of $344,176 and almost double the original cost. A staff report explained the cost estimate was raised due to an increase in land parcel size, a re-alignment of the storm and sewage system, and the addition of contingency costs, which were not originally included. Harper expressed hope for a lower final cost because of the favorable construction market.

“We’re hoping to be under construction within about six months,” said Harper. “There’s 15 acres of impervious area that we can immediately treat and prevent those pollutants from reaching our water supply.”

Harper also said a grant had been awarded to the Rivanna River Basin Commission and $120,000 would be provided to help fund the Crozet stormwater management project. However, Harper warned the Board of the lengthy process to receive the grant.

Supervisor David Slutzky (Rio) said he was concerned with the total balance of the Stormwater Control Improvement Fund due to pending improvement of Sun Ridge Road. The Board approved the renovation of Sun Ridge Road on March 7, 2007 and drainage issues were to be addressed and financed by the Stormwater Fund. Slutzky said the drainage improvements have not been dealt with at the present time and wanted to confirm there would be sufficient funding in the future.

Harper told Slutzky he did not know the balance of the fund but assured him there would excess money left in the fund after the stormwater project. County executive Bob Tucker said the Sun Ridge Road project money had been set aside and its funding would not be depleted by the stormwater project.

Supervisor Ann Mallek (White hall) commented that the Birnam Basin project in 2004 was similar in cost and did not have as many features.

Harper agreed and said the Birnam Basin, a detention basin near Charlotte Humphris Park, cost $720,000 and was much simpler than the stormwater project, which will serve 30 impervious acres.

TIMELINE FOR PODCAST

  • 01:00 - Greg Harper begins presentation
  • 09:09 - David Slutzky asks how the program will be affected by density
  • 11:36 - Ken Boyd asks when construction will begin
  • 12:20 - Larry Davis comments on offsite drainage costs
  • 14:36 - Ann Mallek asks how small developments will pay
  • 19:45 - Slutzky asks about Stormwater Control Improvement Fund
  • 21:20 - Mallek compares project to Birnam Basin

TrackBack

TrackBack URL for this entry:
http://www.typepad.com/services/trackback/6a00d834519bec69e2011570aeac29970c

Listed below are links to weblogs that reference Board of Supervisors support Crozet stormwater management system; Cost higher than original estimate:

Comments

Feed You can follow this conversation by subscribing to the comment feed for this post.

I'd like to clarify that the original cost estimate provided to the Board in 2007 was developed in house and not by the consultant, Kimley-Horn. Being only a concept at the time, the preliminary estimate was based on generalized cost equations and assumptions about anticipated project footprint and local land cost. In addition, it should be noted that the dollars indicated in the article reflect net project cost (after cost recovery such as grant and proffer money). The cost estimate has increased, but not by as high a percentage as is suggested by the article. Lastly, the Board will not be re-examining additional cost estimates at a future time but rather the cost recovery mechanism in which developers within the watershed of the project will make pro rate payments to the County in lieu of providing onsite stormwater management for new development and re-development.